BAPL has been signed MOU with the Government of Chhattisgarh and is intended to set up the integrated steel, power and cement plant in Phase I and Phase II. The proposed production capacity for these units as follows:

 

The integrated steel plant will comprise of sponge iron unit, induction furnace, beneficiation and pellatization plant, blast furnace and rolling mill. The productions from the different units of the integrated steel plants have been phased out in Phase I & Phase II.

 

Site Specific Details

District & State                

Bastar, Chhattisgarh

Block

Tokapal

Village

Raikot

Land Availability

Total Area                    : 309.15 Acres

Nature of the Area       

Plain with gentle rolling at places and mostly covered with laterite soil

Toposheet No

65 E/16

Latitude

19000'05" N to 19000'07" N

Longitude

81050'12" E to 81050'16" E

GENERAL CLIMATIC CONDITIONS (As per IMD, Jagdalpur data between 1951 to 1980)

Average Annual Maximum Temperature

31.4°C

Average Annual Minimum Temperature

19.2°C

Total Annual Rainfall

2395.2 mm

Predominant Wind direction during study period

From South

Elevation of the project site

595m  to 610m above MSL

Accessibility

Road Connectivity

Site can be approach by Jagdalpur - Dantewada State Highway near village Raikot.  The site is located at a distance of about 15 km from Jagdalpur town

Rail Connectivity

Nearest railhead is Jagdalpur Railway Station on Kottavalasa-Kirandaul Branch line of South Eastern Railway (DBKRP) about 15 kms distance.

Nearest Habitation

Village Raikot (about 1.0km from site)

Ecological Sensitive Zone, Archceological Monument, Defence Installation

There is no Ecological Sensitive Zone, Archceological Monument, Defense Installation within 10 km radial zone from the plant area

Iron Ore Mines

Allocated by Government which is about 83 Kms towards Barsoor, Geedam

Coal Block

Allocated in Korba Sector   

Lime Stone Mine

Proposed in discussion with government Raikot & Chitapur with proven deposit 

 

Step taken to-date for implementation of proposed project:

 

  • We have already applied for Environment clearance with Ministry of Environment & Forest, New Delhi and necessary TOR issued by the Ministry. We are preparing IA/EMP Report for the proposed project.

 

  • In the meantime, we have already received Consent to establish final permission From Pollution department related to Arc Furnace & Pelletizing Plant (will be commissioned by March, 2011) and the Arc Furnace is commissioned & Ground work for Pelletizing Plant is already started.

 

  • For occupation of Land at Jagdalpur & Tilda, we have already applied to CSIDC through SIPB. Already acquired at Jagdalpur 49 + 15 = 64 Acres and rest of land acquire work under process.

 

 

  • 8 MW Power at Raipur will be commissioned by next year, as per SBI Schedule.

 

  • Water - We have already applied for Water with Water Resources Deptt. for supply of Water from Kanger River and the department has sanctioned the same and we deposited the amount of commitment charges.

 

  • Coal - Already applied for Coal Linkage with Ministry of Coal, New Delhi for Raipur & Jagdalpur apart from coal block allotted.